Thursday 27 June 2013

Rain and more rain.

The rain has not let up for almost 2 weeks now. Site Supervisor called yesterday to say he will give us a weekly update. He also said the slab can't be laid in this weather. Still raining now which is disappointing. Hopefully it stops soon, so we can move on.

Monday 24 June 2013

Great to see some changes

Piering done, as is the plumbing that goes under the slab. Saw site yesterday whole bunch of foam has been delivered in bundles, waiting for the slab to be poured. Current weather is terrible, heavy rain, forecast is clearing in a couple of days, would be good to see slab this week, but depends on weather. HNere are couple of photos on how it's looking now.

Sunday 16 June 2013

Almost, not quite

Still no digging, had to send some paperwork by post which should have arrived overnight, but it took a whole week, we ended up delivering it by hand, just to make sure they have it. As that is the final step before they start, confident the digging will start this week. No major changes so no new photos, but there is a porta loo on site now, who thought having a portable toilet on a block of land would add to our excitement.

Sunday 2 June 2013

No changes after weekend

Went to check out the land last night to see if there has been any digging, but none, I would have said the rain has held it up, BUT next door has had there's dug up, looks like their builder is a little quicker. Would hope it will be this week.